• EU HRC (N. Europe)€750–795/tex-works N. Europe; German mill offers €775–795/t; seller deals €750–760/t for December and offers €770–785/t ex-works; trade source said prices below €785/t no longer seen at mills; Fastmarkets index €775.63/t on 18 Nov18 Nov 2026 · Fastmarkets via EUROMETAL
  • China steel exports9.854 MtOctober; Jan–Oct 95.495 Mt, −2.3% y/y10 Nov 2026 · China Customs via Mysteel / SMM
  • World crude steel142.4 MtSeptember, −0.2% y/y23 Oct 2026 · worldsteel
  • Iron ore fines 61%$89.10/dmtseaborne 61% fines, SMM; unchanged d/d20 Nov 2026 · SMM via Hellenic Shipping News
  • Turkish HMS 1&2 (80:20)$397/tCFR, October average11 Nov 2026 · GMK Center
  • EU CBAM certificate€82.32Q3 2026 price, per certificate5 Oct 2026 · European Commission
  • US Section 232 steel10%–50%tariff, by product/country8 Oct 2026 · Congressional Research Service

voestalpine’s Linz electric arc furnace gets its 220 kV power link: lower-CO₂ flat steel from 2027 looks firmer, but blast furnaces run until 2029

APG has energised the Hütte Süd substation that will feed voestalpine’s first Linz EAF, due in the first half of 2027. Loharo sets out the company’s figures, what they imply per tonne, and what flat-steel buyers should ask for in 2027 contracts.

By Mara AlvestadPublished 5 min read
Illustration: graphite electrode columns and clamps above an electric arc furnace
Illustration of electric arc furnace electrodes

The power connection for voestalpine’s first electric arc furnace (EAF) in Linz is now live. Austrian grid operator APG said on 17 November that its new Hütte Süd substation, the direct 220 kV supply point for voestalpine, and the first two of four new line sections are in operation (APG). The Linz EAF is due to start in the first half of 2027 (OÖ Nachrichten), and voestalpine’s chief executive said the programme is on time and on budget. For EU buyers of flat steel, the start of lower-CO₂ steel from Linz in 2027 now looks firmer. No step is needed yet. If you plan to buy voestalpine’s CO₂-reduced greentec steel in 2027, ask now how much EAF-route material your contract will carry and how its carbon value is measured.

What is new since our October report

When Loharo reported on 14 October that the Donawitz EAF had been installed (voestalpine completes EAF installation at Donawitz), first melts at both Donawitz and Linz were planned for the first half of 2027. Our 11 November results piece covered the Steel Division’s weaker revenue (voestalpine’s steel revenue falls 15%). What is new is that the grid hurdle in Linz has been cleared. The 2023 plan already pointed to a 220 kV line feeding the furnace from 2027 (voestalpine, October 2023), and that connection is now energised. Chief executive Herbert Eibensteiner said in APG’s release that the €1.5 billion first step is on schedule and within budget, that one blast furnace at each site is to close by 2029, and that CO₂ emissions should fall by up to 30% by 2029 compared with 2019 (APG). Salzgitter cleared a similar hurdle in October (Salzgitter’s 380 kV line).

Advertise

Reach steel buyers and importers worldwide

Put your brand in front of the people who buy and trade steel.

Advertise with Loharo
ItemFigureSource and timing
Linz EAF outputabout 1.6 Mt a year of CO₂-reduced steelvoestalpine, 2023; start H1 2027
Donawitz EAF outputabout 850,000 t a yearvoestalpine, 2023; first melts H1 2027
First-step investmentabout €1.5bn, of which Linz about €1bnvoestalpine, 2023; on budget (CEO, 17 Nov 2026)
Blast furnaces closedone at each siteby 2029 (CEO, 17 Nov 2026)
CO₂ cutup to 30% vs 2019; almost 4 Mt a yearby 2029 (2026); 4 Mt estimate from 2023
Grid project, Upper Austria€800m; 780 MVA to 3,400 MVAAPG; complete in 2030
Loharo table from voestalpine’s and APG’s own figures (voestalpine, March 2023; voestalpine, October 2023; APG, 17 November 2026).

Loharo calculation: what the company figures imply

MeasureWorkingResult
Investment per tonne of yearly EAF capacity, Linz€1.0bn ÷ 1.6 Mtabout €625 a tonne
Same, Donawitz(€1.5bn − €1.0bn) ÷ 0.85 Mtabout €590 a tonne
CO₂ saved per tonne moved to the EAF routealmost 4 Mt ÷ about 2.5 Mtup to about 1.6 t CO₂ a tonne
Grid capacity in central Upper Austria3,400 MVA ÷ 780 MVAabout 4.4 times
Loharo calculation from the company figures above. The CO₂ figure is voestalpine’s 2023 estimate divided by the planned EAF output; it is a group average, not a product carbon footprint.

The CO₂ row matters most for buyers. A saving of up to about 1.6 t of CO₂ for each tonne moved from blast furnace to EAF is large, but it applies to the EAF share only. Linz keeps running blast furnaces next to the new furnace until at least 2029, so in 2027 a large part of voestalpine’s steel will still come from the blast-furnace route.

What this means for buyers

For EU buyers of flat steel, the live grid link removes one of the main risks to a 2027 start of lower-CO₂ steel from Linz, but the furnace still has to be commissioned and ramped up. Treat 2027 volumes of greentec steel as likely but not guaranteed.

If low-CO₂ steel matters for your 2027 contracts, ask voestalpine to state the EAF-route volume, the carbon value per tonne and how it is calculated, and what you receive if the ramp-up slips.

What to watch

  • First heat in the Linz EAF, due in the first half of 2027, and the first melts at Donawitz.
  • voestalpine’s third-quarter report for 2026/27, and any update on the second step (another blast furnace at each site from 2030, not yet approved).

Verification status: Verified

  • The grid milestone and the chief executive’s statements are from APG’s 17 November release; capacities and investment are voestalpine’s own figures from 2023, and the Linz start date is reported by OÖ Nachrichten. Per-tonne figures are Loharo calculations with the inputs shown.
  • Key: Verified = material factual claims are supported by an appropriate primary source or clearly attributed reporting/market assessments; Partially verified = a specific material claim remains unsupported, contradicted or materially overstated; Analysis = interpretation or forecast with sourced premises; Developing = material facts are checked but the situation is still changing.

Sources

Primary sources

Supporting sources

Last fact-check: 23 November 2026.

Planning steel imports into the EU? Estimate CBAM costs with the free calculator using EU default values. For supplier-specific emissions and a portfolio review, see the CBAM Cost Check.

Ask the Analyst

“What could CBAM add to Indian HRC delivered to Rotterdam in 2027?”: landed cost with duty, quota and CBAM in one answer.Ask the Analyst

Facts, analysis and uncertainty are labelled in line with our editorial standards. Report an error – corrections are dated and noted on the article. Information and analysis only, not investment advice.