The power connection for voestalpine’s first electric arc furnace (EAF) in Linz is now live. Austrian grid operator APG said on 17 November that its new Hütte Süd substation, the direct 220 kV supply point for voestalpine, and the first two of four new line sections are in operation (APG). The Linz EAF is due to start in the first half of 2027 (OÖ Nachrichten), and voestalpine’s chief executive said the programme is on time and on budget. For EU buyers of flat steel, the start of lower-CO₂ steel from Linz in 2027 now looks firmer. No step is needed yet. If you plan to buy voestalpine’s CO₂-reduced greentec steel in 2027, ask now how much EAF-route material your contract will carry and how its carbon value is measured.
What is new since our October report
When Loharo reported on 14 October that the Donawitz EAF had been installed (voestalpine completes EAF installation at Donawitz), first melts at both Donawitz and Linz were planned for the first half of 2027. Our 11 November results piece covered the Steel Division’s weaker revenue (voestalpine’s steel revenue falls 15%). What is new is that the grid hurdle in Linz has been cleared. The 2023 plan already pointed to a 220 kV line feeding the furnace from 2027 (voestalpine, October 2023), and that connection is now energised. Chief executive Herbert Eibensteiner said in APG’s release that the €1.5 billion first step is on schedule and within budget, that one blast furnace at each site is to close by 2029, and that CO₂ emissions should fall by up to 30% by 2029 compared with 2019 (APG). Salzgitter cleared a similar hurdle in October (Salzgitter’s 380 kV line).
Reach steel buyers and importers worldwide
Put your brand in front of the people who buy and trade steel.
Advertise with Loharo| Item | Figure | Source and timing |
|---|---|---|
| Linz EAF output | about 1.6 Mt a year of CO₂-reduced steel | voestalpine, 2023; start H1 2027 |
| Donawitz EAF output | about 850,000 t a year | voestalpine, 2023; first melts H1 2027 |
| First-step investment | about €1.5bn, of which Linz about €1bn | voestalpine, 2023; on budget (CEO, 17 Nov 2026) |
| Blast furnaces closed | one at each site | by 2029 (CEO, 17 Nov 2026) |
| CO₂ cut | up to 30% vs 2019; almost 4 Mt a year | by 2029 (2026); 4 Mt estimate from 2023 |
| Grid project, Upper Austria | €800m; 780 MVA to 3,400 MVA | APG; complete in 2030 |
Loharo calculation: what the company figures imply
| Measure | Working | Result |
|---|---|---|
| Investment per tonne of yearly EAF capacity, Linz | €1.0bn ÷ 1.6 Mt | about €625 a tonne |
| Same, Donawitz | (€1.5bn − €1.0bn) ÷ 0.85 Mt | about €590 a tonne |
| CO₂ saved per tonne moved to the EAF route | almost 4 Mt ÷ about 2.5 Mt | up to about 1.6 t CO₂ a tonne |
| Grid capacity in central Upper Austria | 3,400 MVA ÷ 780 MVA | about 4.4 times |
The CO₂ row matters most for buyers. A saving of up to about 1.6 t of CO₂ for each tonne moved from blast furnace to EAF is large, but it applies to the EAF share only. Linz keeps running blast furnaces next to the new furnace until at least 2029, so in 2027 a large part of voestalpine’s steel will still come from the blast-furnace route.
What this means for buyers
For EU buyers of flat steel, the live grid link removes one of the main risks to a 2027 start of lower-CO₂ steel from Linz, but the furnace still has to be commissioned and ramped up. Treat 2027 volumes of greentec steel as likely but not guaranteed.
If low-CO₂ steel matters for your 2027 contracts, ask voestalpine to state the EAF-route volume, the carbon value per tonne and how it is calculated, and what you receive if the ramp-up slips.
What to watch
- First heat in the Linz EAF, due in the first half of 2027, and the first melts at Donawitz.
- voestalpine’s third-quarter report for 2026/27, and any update on the second step (another blast furnace at each site from 2030, not yet approved).
Verification status: Verified
- The grid milestone and the chief executive’s statements are from APG’s 17 November release; capacities and investment are voestalpine’s own figures from 2023, and the Linz start date is reported by OÖ Nachrichten. Per-tonne figures are Loharo calculations with the inputs shown.
- Key: Verified = material factual claims are supported by an appropriate primary source or clearly attributed reporting/market assessments; Partially verified = a specific material claim remains unsupported, contradicted or materially overstated; Analysis = interpretation or forecast with sourced premises; Developing = material facts are checked but the situation is still changing.
Sources
Primary sources
- APG, “Meilenstein für die Energiezukunft Oberösterreichs: Umspannwerk Hütte Süd und erste Projektabschnitte in Betrieb”, 17 November 2026 (German)
- voestalpine, “voestalpine Supervisory Board approves EUR 1.5 billion for further decarbonization”, 22 March 2023
- voestalpine, “Start of construction for voestalpine greentec steel in Linz”, 10 October 2023
Supporting sources
- OÖ Nachrichten, “Stromversorgung: Die ‚Steckdose der voestalpine‘ ist in Betrieb gegangen”, 17 November 2026 (German)
- SteelOrbis, “Austria commissions new power infrastructure to support voestalpine’s EAF transition”, 20 November 2026
- Loharo, “voestalpine completes EAF installation at Donawitz”, 14 October 2026
Last fact-check: 23 November 2026.