ArcelorMittal’s new electric arc furnace (EAF) in Dunkirk now has a supplier and a start date. Italian plant builder Danieli said on 23 November that ArcelorMittal has chosen it to supply the furnace, a 300-tonne Danieli Digimelter with a capacity of 2 million tonnes a year, and that start-up is scheduled for 2029 (Danieli). For EU buyers of flat steel, this gives the first dated start for lower-CO₂ steel from ArcelorMittal’s largest French site. No step is needed yet. If you plan to buy lower-CO₂ coil from Dunkirk from 2029, ask which CO₂ value per tonne will apply to your product and which mix of raw materials it assumes.
What is new since our October report
When Loharo reported on 16 October that ArcelorMittal had committed €300 million of the €1.3 billion project and opened the public consultation, the company’s statement gave no start-up date (ArcelorMittal commits €300 million to 2 Mt/y Dunkirk EAF). Danieli’s release now gives 2029. It also names the main equipment: the furnace is powered by Danieli’s Q-ONE digital power system, and the order covers a fume treatment plant, material handling systems and the complete electrical and automation package. Danieli repeats ArcelorMittal’s figure that the furnace will make steel with about 0.6 tonnes of CO₂ per tonne, three times less than the blast furnace route, using a mix of scrap, HBI or DRI and hot metal. SteelOrbis reported the same details on 24 November (SteelOrbis). Neither release gives the value of the order.
Reach steel buyers and importers worldwide
Put your brand in front of the people who buy and trade steel.
Advertise with LoharoLoharo calculation: what the project figures imply
| Measure | Working | Result |
|---|---|---|
| Investment per tonne of yearly capacity, Dunkirk | €1.3bn ÷ 2 Mt | about €650 a tonne |
| Same, voestalpine Linz EAF (for comparison) | €1.0bn ÷ 1.6 Mt | about €625 a tonne |
| Blast furnace route implied by “three times less” | 0.6 t × 3 | about 1.8 t CO₂ a tonne |
| CO₂ saved per tonne moved to the EAF | 1.8 t − 0.6 t | about 1.2 t CO₂ a tonne |
| Heats a day at full capacity | 2,000,000 t ÷ 300 t ÷ 365 | about 18 |
Analysis. At about €650 a tonne of capacity, Dunkirk costs about the same per tonne as voestalpine’s Linz furnace, though the two projects’ scopes are not identical. The CO₂ figure depends on the charge: 0.6 tonnes is the project figure for a mix that includes hot metal from the blast furnaces, so the value for a given order may differ, and buyers should not assume it applies to every tonne.
What this means for buyers
For EU buyers of flat steel, Dunkirk’s EAF becomes a dated source of lower-CO₂ steel from 2029, but nothing changes in supply before then. The releases do not say how much blast furnace output the furnace will replace.
In contracts for lower-CO₂ coil from Dunkirk from 2029, ask ArcelorMittal for the CO₂ value per tonne of your product, the charge mix behind it, and what applies if the start-up slips.
What to watch
- The end of the public consultation on the furnace permits on 15 January 2027, as set out in our October report, and the permit decisions.
- Any ArcelorMittal statement on the furnace start-up, the share of scrap and DRI in the charge, and the blast furnace it will replace.
Verification status: Verified
- The supplier, equipment, capacity, 2029 start-up and CO₂ figure are from Danieli’s 23 November release, which repeats ArcelorMittal’s project figures; SteelOrbis reports the same. Per-tonne figures are Loharo calculations with the inputs shown.
- Key: Verified = material factual claims are supported by an appropriate primary source or clearly attributed reporting/market assessments; Partially verified = a specific material claim remains unsupported, contradicted or materially overstated; Analysis = interpretation or forecast with sourced premises; Developing = material facts are checked but the situation is still changing.
Sources
Primary sources
Supporting sources
- SteelOrbis, “ArcelorMittal selects Danieli for 2 million mt EAF project in Dunkirk”, 24 November 2026
- Loharo, “ArcelorMittal commits €300 million to 2 Mt/y Dunkirk EAF as consultation opens”, 16 October 2026
- Loharo, “voestalpine’s Linz electric arc furnace gets its 220 kV power link”, 23 November 2026
Last fact-check: 25 November 2026.