thyssenkrupp Steel has opened a tender for hydrogen for its new direct reduction plant in Duisburg, but the first tranche is small and late. The company said on 23 November that it expects to buy about 20,000 to 40,000 tonnes of hydrogen a year, with deliveries starting in 2031, and that hydrogen will at first replace only part of the natural gas in the plant (thyssenkrupp Steel). For EU buyers of flat steel, this means low-CO₂ steel from the new plant, due to start in 2029, will rest on natural gas for its first years. No step is needed yet. If you are negotiating low-CO₂ coil from thyssenkrupp for delivery in 2029 or later, ask whether the CO₂ figure per tonne assumes natural gas or a hydrogen share.
What is new since our November reports
On 2 November Loharo reported that revised aid terms let thyssenkrupp run the plant on natural gas for longer, and that a hydrogen tender would “start shortly”, with no date for hydrogen use (thyssenkrupp can run its Duisburg DRI plant on natural gas for longer). On 12 November we reported that the plant’s start had moved to 2029 (thyssenkrupp confirms its Duisburg DRI plant slips to 2029). What is new is the size and timing of the hydrogen step. Suppliers can register until 17 December 2026, after which bidding begins, and the final volume will depend on the bids received, largely on their commercial terms, the company said. According to the company, the gradual switch meets the Commission’s state aid conditions and the terms of the grant now set by the German federal government and North Rhine-Westphalia.
Reach steel buyers and importers worldwide
Put your brand in front of the people who buy and trade steel.
Advertise with LoharoThe plant itself is unchanged: 2.5 million tonnes a year of direct reduced iron (DRI) feeding two melters with 2.3 million tonnes of hot metal capacity. thyssenkrupp says that on natural gas alone it cuts CO₂ by more than 50% compared with the blast furnace route, and that full hydrogen operation, which it now plans “at a later stage”, could avoid about 3.5 million tonnes of CO₂ a year. The trade site gasworld notes that the tender does not specify the hydrogen criteria or give a timeline for full hydrogen operation (gasworld).
Loharo calculation: the tender against the 2023 plan
| Measure | Working | Result |
|---|---|---|
| First tranche as a share of the 2023 plan | 20,000 t ÷ 143,000 t; 40,000 t ÷ 143,000 t | about 14% to 28% |
| Hydrogen per tonne of DRI capacity, new tranche | 20,000 t ÷ 2.5 Mt; 40,000 t ÷ 2.5 Mt | about 8 to 16 kg a tonne |
| Same, 2023 plan | 143,000 t ÷ 2.5 Mt | about 57 kg a tonne |
| Hydrogen timing | “as early as 2029” in the 2023 plan; first deliveries in 2031 now | about two years later |
Analysis. On these figures, the first tranche would cover well under a third of the hydrogen thyssenkrupp planned for 2029 in 2023. The rest of the reduction work would fall to natural gas, unless the company buys more hydrogen later. That is consistent with its own wording that hydrogen will at first replace only part of the gas. The plant would still cut CO₂ by more than half against the blast furnace, the company says, but its steel would not reach the much lower CO₂ level that full hydrogen operation promises until an unnamed later date.
What this means for buyers
For EU buyers of flat steel, the tender confirms that thyssenkrupp’s new low-CO₂ route will start on natural gas in 2029 and add only a limited hydrogen share from 2031. The tender does not change the plant’s planned capacity.
In low-CO₂ supply contracts running to 2031 or later, ask thyssenkrupp to state the CO₂ value per tonne, whether it assumes natural gas or a hydrogen share, and whether the value or the premium changes when hydrogen is introduced.
What to watch
- 17 December 2026: supplier registration closes and the bidding phase begins.
- The awarded volume and price, and whether the tender requires renewable or other low-carbon hydrogen.
- Commissioning of the plant, now due in 2029, and any date for full hydrogen operation.
Verification status: Verified
- The tender, its volume, timing and the plant figures are from thyssenkrupp Steel’s 23 November release; the 2023 hydrogen plan is from its July 2023 release, and the missing hydrogen criteria are as reported by gasworld. Shares and per-tonne figures are Loharo calculations with the inputs shown.
- Key: Verified = material factual claims are supported by an appropriate primary source or clearly attributed reporting/market assessments; Partially verified = a specific material claim remains unsupported, contradicted or materially overstated; Analysis = interpretation or forecast with sourced premises; Developing = material facts are checked but the situation is still changing.
Sources
Primary sources
- thyssenkrupp Steel, “thyssenkrupp Steel launches hydrogen tender to supply its direct reduction plant in Duisburg”, 23 November 2026
- thyssenkrupp Steel, “EU Commission approves German federal and state government funding for thyssenkrupp Steel’s tkH2Steel decarbonization project”, 20 July 2023
Supporting sources
- gasworld, “Thyssenkrupp Steel launches hydrogen tender for DRI plant transition from 2031”, 24 November 2026
- SteelOrbis, “Thyssenkrupp Steel launches new hydrogen supply tender for Duisburg direct reduction plant”, 24 November 2026
- Loharo, “thyssenkrupp can run its Duisburg DRI plant on natural gas for longer”, 2 November 2026
- Loharo, “thyssenkrupp confirms its Duisburg DRI plant slips to 2029”, 12 November 2026
Last fact-check: 25 November 2026.